Weekly Update: March 22, 2018

March 22, 2018

Check out March 22nd’s Kingfish Bay Construction Updates!

Some “Finishing Up” and beautiful “New Beginnings” at Kingfish Bay!

  • Pool is formed for C-3 Bonita
  • Drywall has been installed in C-3 Bonita
  • C-4 Albacore II is under roof
  • Drywall has been installed in C-6 Albacore
  • Tile is installed in the bathrooms of C-10 Albacore
  • Landscaping around C-10 Albacore and C-11 Cobia
  • Interior and exterior lighting fixtures have been installed in CV-3 Marlin