Weekly Update: November 21, 2019

November 21, 2019

Check out November 21st’s Kingfish Bay Construction Updates.

What a wonderful community to call home!

  • Roof installation complete C-12 Albacore II
  • Prepping for slab C-21 Albacore II
  • Siding installation almost complete C-40 Albacore II
  • Prepped and ready for slab C-38 Anchor Coral II
  • Siding installation almost complete B-22 Angelfish
  • Walkway poured for B-2 Seahorse
  • Interior trim installed and walls primed B-2 Seahorse
  • Roof installed B-3 Seahorse
  • Roof installed B-29 Seahorse
  • Shutters and front door painted B-31 Seahorse
  • Exterior railing on second story installed Parrotfish II C-23
  • Master shower accent tile SF-27 Amberjack
  • Starting to trim exterior for siding C-43 Hawkfish